LCRA's fiscal 2027 plan: a $656 million operating budget, $1.8 billion in capital, $8.6 billion for transmission and Highland Lakes near 98% full in late 2026.

Quick Answer: The Lower Colorado River Authority is operating under a fiscal 2027 business plan with a $656 million operating budget and about $1.8 billion in capital spending, the largest plan in its history. Roughly $1.5 billion of this year’s capital goes to transmission, part of an $8.6 billion five-year grid program. The plan projects about $1.99 billion in revenue, while Lakes Travis and Buchanan sit at roughly 98% of water supply capacity as of late November 2026.

The Lower Colorado River Authority, the Austin-based public utility that manages the Highland Lakes, sells wholesale electricity to 34 customers (29 city utilities, four electric cooperatives and WSC Energy II) and runs one of the largest transmission networks in the state, is in the fifth month of the biggest spending plan it has ever adopted. Its board approved the fiscal 2027 business and capital plans in May 2026, and the fiscal year began July 1, 2026.

For Central Texas businesses, LCRA is easy to overlook because it sends almost no retail bills. Yet the wholesale power behind cooperatives such as Bluebonnet and Pedernales and city utilities such as Bastrop and San Marcos, the water the region draws from Lake Travis, and many of the high-voltage lines that tie Austin to the rest of the grid all run through this one agency. Here is the plan by the numbers, taken from LCRA’s own published documents.

How big is LCRA’s fiscal 2027 budget?

LCRA’s fiscal 2027 plan authorizes $655.6 million in operations spending and about $1.81 billion in capital investment, both records for the agency. A year earlier the board approved a $591.4 million operating budget and about $1.63 billion in capital spending for fiscal 2026, so both lines grew about 11% in a single year.

LCRA says the plan is funded mainly from its own revenues and debt, with no state appropriations. The business plan projects total fiscal 2027 revenue of $1,991.8 million against operating expenses of $1,115.6 million, leaving a net operating margin of $876.2 million. Debt service takes $600.5 million of that, which leaves about $275.6 million after debt payments. Put another way, about 30 cents of every revenue dollar goes to bondholders.

LCRA key facts Figure
Fiscal 2027 start date July 1, 2026
Projected total revenue $1,991.8 million
Authorized operations spending $655.6 million
Capital budget About $1.81 billion
Five-year capital budget (fiscal 2027 to 2031) About $9.9 billion
Debt service $600.5 million
Consolidated debt service coverage 1.46 times
Budgeted positions 2,723 (up 161)
Wholesale electric customers 34
Parks More than 40, on nearly 11,000 acres

How does fiscal 2027 compare with fiscal 2026?

Every headline number is higher, and the five-year transmission commitment grew fastest. The transmission program was about $5.9 billion in the plan approved in May 2025 and is about $8.6 billion in the current plan, an increase of roughly 46% in twelve months.

Measure Fiscal 2026 plan Fiscal 2027 plan Change
Operating budget $591.4 million $655.6 million Up about 11%
Capital budget About $1.63 billion About $1.81 billion Up about 11%
Five-year transmission capital About $5.9 billion About $8.6 billion Up about 46%
Transmission revenue $823.0 million (budget) $924.9 million Up about 12%

Where does LCRA’s money come from?

Transmission is the largest disclosed revenue source, at $924.9 million, or about 46% of the $1,991.8 million total projected for fiscal 2027. Water brings in $48.3 million, Strategic Services $25.8 million and the Public Service Fund $6.4 million.

The wholesale power business accounts for most of the remainder, but LCRA marks its wholesale power financials as confidential and removes rate and cost-per-megawatt-hour figures from the public version of the plan because the agency competes in the Texas power market. That is why this article cannot give a wholesale power rate. The plan does disclose that wholesale power debt service coverage is expected to run between 1.28 and 1.40 times over the five-year period.

How much is LCRA spending on transmission?

LCRA Transmission Services Corporation, the affiliate that owns the transmission system, plans about $1.49 billion of capital spending in fiscal 2027 and about $8.59 billion over fiscal 2027 through 2031. That is roughly 87% of the $9.9 billion LCRA expects to invest across all of its businesses in five years.

The fiscal 2027 transmission figure of $1,487.7 million includes $490.1 million for projects already approved and $997.6 million set aside for future projects. The driver is load growth. The plan assumes ERCOT 4CP, a measure of peak demand on the state grid, grows between 4.5% and 6.5% each year from calendar 2027 through 2031.

Which transmission projects are named in the plan?

The plan names individual substation and line projects, including a power transformer upgrade at Georgetown. The largest by fiscal 2027 spending are below.

Project Fiscal 2027 spending Lifetime budget
Bakersfield Dynamic Reactive Substation Upgrade $81.5 million $215.0 million
Georgetown Power Transformer Upgrade $35.1 million $64.4 million
Kendall-Welfare Transmission Line Upgrade $35.0 million $122.0 million
Big Hill-Kendall Transmission Line Storm Hardening $19.9 million $34.7 million
Bearkat-North McCamey Transmission Line Addition $12.3 million $260.3 million
North McCamey-Sand Lake Transmission Line Addition $2.2 million $293.0 million

How is the transmission buildout paid for?

Mostly with debt, repaid through regulated transmission rates. Of the $1.81 billion fiscal 2027 capital budget, $1,545.8 million is debt funded, and only about 14% is paid from revenue or third-party proceeds.

The transmission affiliate projects $924.9 million of revenue in fiscal 2027, $188.0 million of operations and maintenance expense, and $443.0 million of debt service, for coverage of 1.39 times. After debt service it expects $171.0 million of net margin, of which $105.1 million goes back into capital projects. The plan keeps coverage between 1.32 and 1.49 times through the period.

LCRA Transmission Services Corporation also plans a transmission cost of service rate case using fiscal 2027 as the test year, with new rates expected to take effect in fiscal 2029. The plan assumes coverage of 1.60 times for fiscal 2029 through 2031 in that case. That is a planning assumption, not an approved rate.

What new power plants has LCRA built?

LCRA’s newest plant is the Timmerman Power Plant near Maxwell in Caldwell County, a two-unit natural gas peaker of about 380 megawatts that became fully operational in April 2026. The first unit connected to the grid in August 2025 and the second followed in April 2026, a month ahead of schedule, according to the governor’s office, which described Timmerman as the first Texas Energy Fund-supported project to come fully online.

A peaker plant is built to start and stop within minutes when demand spikes or other generation drops off. LCRA says Timmerman can supply more than 100,000 homes at full output. Ground was broken in April 2024, so the plant went from groundbreaking to full operation in two years.

How much generation does LCRA have in the Austin area?

LCRA reports about 4,100 megawatts of owned or contracted power, and a large share of the plants sit in the counties around Austin. Bastrop County alone hosts 1,160 megawatts across the Lost Pines 1 and Sim Gideon plants.

Facility County Fuel Listed capacity
Fayette Power Project Fayette Coal 1,642 MW
Sim Gideon Power Plant Bastrop Natural gas 620 MW
Thomas C. Ferguson Power Plant Llano Natural gas 556 MW
Lost Pines 1 Power Project Bastrop Natural gas 540 MW
Timmerman Power Plant Caldwell Natural gas 372 MW
Winchester Power Park Fayette Natural gas 184 MW
Six Highland Lakes dams Burnet, Llano, Travis Hydroelectric 295 MW combined

Two cautions apply to the table. The Fayette Power Project is co-owned with Austin Energy, which shares Units 1 and 2, so LCRA’s own share is smaller than the plant total. And LCRA’s facility list shows Timmerman at 372 megawatts while its project page and the governor’s office describe it as about 380 megawatts. Mansfield Dam, which forms Lake Travis, is the largest hydroelectric station at 108 megawatts.

How full are the Highland Lakes right now?

Lakes Travis and Buchanan, the two water supply reservoirs in the chain, held a combined 1.93 million acre-feet in late November 2026, about 98% of their 1.96 million acre-feet of conservation capacity, based on Texas Water Development Board readings. Lake Travis was 99.9% full on November 26 and Lake Buchanan was 96.5% full on November 24.

Measure Lake Travis (Nov. 26, 2026) Lake Buchanan (Nov. 24, 2026)
Percent full 99.9% 96.5%
Water level 680.97 feet 1,018.63 feet
Conservation storage 1,097,473 acre-feet 836,138 acre-feet
Conservation capacity 1,098,044 acre-feet 866,694 acre-feet
Percent full six months earlier 78.1% 98.8%
Percent full one year earlier 80.2% 96.7%

The swing at Lake Travis is the story. The lake held 857,365 acre-feet on May 26, 2026, and 1,097,473 acre-feet six months later, a gain of about 240,000 acre-feet. Most of that arrived in July. In a July 18, 2026 release, LCRA said some parts of the Hill Country had received more than 20 inches of rain in a week, that Lakes Buchanan and Travis had filled for the first time since 2019, and that combined storage stood slightly above 100%.

Lake Travis is considered full for water supply at 681 feet above mean sea level, and its flood pool can hold another 776,000 acre-feet above that. At 680.97 feet on November 26, the lake is within a fraction of an inch of full.

What is LCRA spending on water supply and dams?

The fiscal 2027 plan sets aside about $152.6 million over five years for new water supply projects and about $30.3 million for dam rehabilitation, not counting projects that serve only the hydroelectric plants. Water capital of all kinds totals $194.8 million over the five years. LCRA added Arbuckle Reservoir in Wharton County to the supply system last year and says it is exploring another reservoir in the lower basin, which is a study, not a committed project.

Are LCRA water rates going up?

Yes. The plan raises the firm water rate from $165 to $190 per acre-foot in steps, with increases scheduled for January 2027, January 2029 and January 2031. That is a cumulative increase of about 15%.

Firm water, the supply contracted to cities, industries and utilities, is projected to generate $34.3 million in fiscal 2027, about 71% of all water revenue. The water business shows why the increases are planned: its fiscal 2027 debt service coverage is 0.53 times before adjustments and 1.26 times on the adjusted basis LCRA uses.

Brian’s Take

When I read a utility plan, I go to the debt line first. LCRA expects about $2 billion of revenue and $600 million of debt service this year, and about 85% of a $1.8 billion capital budget is borrowed. That is not a criticism. It is how regulated wires get built, and coverage of 1.46 times is a workable cushion. But it tells me who pays in the end: every business in Texas that pays a transmission charge on its electric bill.

The number I would circle is the jump in the five-year transmission plan from $5.9 billion to $8.6 billion in one year. An agency does not add $2.7 billion to its wire budget on a hunch. It is reading the same load forecasts everyone else is, with peak demand assumed to grow 4.5% to 6.5% a year. Whether that demand shows up on schedule is the open question, and the debt gets issued either way.

On water, I see good fortune more than a solved problem. Lake Travis went from 78% to essentially full in six months because of one very wet July. A full lake buys time. It does not replace the $153 million of new supply projects in the plan, and I would not treat a firm water rate of $190 per acre-foot in 2031 as the last increase Central Texas will see.

Frequently Asked Questions

How much is LCRA’s fiscal 2027 budget?

The plan authorizes $655.6 million in operations spending and about $1.81 billion in capital investment for the year that began July 1, 2026. Projected revenue is $1,991.8 million.

How much will LCRA spend on transmission lines?

About $1.49 billion in fiscal 2027 and about $8.59 billion from fiscal 2027 through 2031, through LCRA Transmission Services Corporation.

How big is the Timmerman Power Plant?

About 380 megawatts across two natural gas peaking units near Maxwell in Caldwell County. It became fully operational in April 2026 and can supply more than 100,000 homes at full output.

How full is Lake Travis?

Lake Travis was 99.9% full at 680.97 feet on November 26, 2026, according to Texas Water Development Board data. It was 80.2% full a year earlier.

What is LCRA’s firm water rate?

The fiscal 2027 plan shows the firm water rate rising from $165 to $190 per acre-foot, with increases in January 2027, 2029 and 2031.

Sources and Further Reading

  1. LCRA Fiscal Year 2027 Business and Capital Plans, Lower Colorado River Authority
  2. LCRA Transmission Services Corporation Fiscal Year 2027 Business and Capital Plans, Lower Colorado River Authority
  3. LCRA commits $1.8 billion for power, water and broadband as Texas continues to grow, Lower Colorado River Authority news release
  4. LCRA Board approves business and capital plans for fiscal year 2026, Lower Colorado River Authority news release
  5. Governor Abbott, LCRA Announce Timmerman Power Plant Is Fully Operational, Office of the Texas Governor
  6. Timmerman Power Plant, A diverse generation fleet and Powering Texas, Lower Colorado River Authority
  7. Lake Travis and Lake Buchanan reservoir pages, Water Data for Texas, Texas Water Development Board
  8. LCRA plans to begin floodgate operations at Buchanan Dam on Sunday, Lower Colorado River Authority news release, July 18, 2026